Summary — what to expect when you build in Sumba
The realities that shape every project we advise on:
- Construction cost per m² is typically 20–40% higher than mainstream Bali for equivalent quality
- Timelines are longer: 14–22 months for a well-built villa, not 8–12
- Materials must be planned in shipments — no next-day runs to a warehouse
- Skilled tradespeople exist but are limited; the good crews are booked out
- Design decisions (roof, orientation, materials) matter more because maintenance is harder
- Permits (PBG, SLF) are non-negotiable and take time — start them at design stage